Concord Construction, Inc.  
Projects >> HEAVY CONCRETE >>
Keechelus Dam Modifications

Keechelus Dam
Completed Maintenance Warehouse
Construction of this building was accomplished as a subcontractor to Kiewit Pacific Co. We submitted a proposal to them to perform the entire scope of work associated with this building while they were the general contractor on the overall project of making safety modification to the entire dam. They welcomed the proposal as we had performed many successful projects for the Bureau of Reclamation and were well suited to perform all the required submittals.
Keechelus Dam
Setting of site cast concrete tilt-up panels
OWNER:
Bureau of Reclamation


LOCATION:
Lake Keechelus near Easton, WA


TOTAL SIZE OF PROJECT:
1,800 sf


DURATION OF PROJECT:
3 months


PROJECT TYPE:
Tilt-up concrete
The construction was tilt-up concrete wall panels with slab on grade and wood trusses with sheathing and standing seam metal roof panels.